North Hoyle

30 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines30
Installed capacity60 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Greencoat (formerly Npower Renewables)
Turbine manufacturerVestas
Turbine modelV80-2.0

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2000 2001 2002 2003 2004 Project timeline Application submitted April 2001 Permission granted July 2002 Under construction April 2003 Operational December 2003

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2494.

What the register tells us

The application was determined in about 15 months. Construction to first power took about 8 months. The scheme has been operating for about 23 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2 MW per turbine on average.