6 turbines · operational · Co. Fermanagh
| Status | Operational |
|---|---|
| County / region | Co. Fermanagh |
| Turbines | 6 |
| Installed capacity | 15 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Natural Power |
| Turbine manufacturer | GE |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 12 years.
The register links a second scheme on this site (REPD ref 4282, Planning Permission Expired): 3 turbines · 2 MW each · applicant Renewable Energy Systems (RES). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4654.
The application was determined in about 63 months. Construction to first power took about 16 months. A planning permission on this site expired in March 2016. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.