Ora More

6 turbines · operational · Co. Fermanagh

Wind farm facts

StatusOperational
County / regionCo. Fermanagh
Turbines6
Installed capacity15 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Natural Power
Turbine manufacturerGE
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2006 2008 2010 2012 2014 2016 2018 2020 Scheme REPD 4654 Application submitted December 2005 Permission granted March 2011 Under construction November 2015 Permission expired March 2016 Operational March 2017 Scheme REPD 4282 Application submitted November 2013 Permission granted December 2015 Permission expired December 2020

From application to operation, this scheme took about 12 years.

The register links a second scheme on this site (REPD ref 4282, Planning Permission Expired): 3 turbines · 2 MW each · applicant Renewable Energy Systems (RES). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4654.

What the register tells us

The application was determined in about 63 months. Construction to first power took about 16 months. A planning permission on this site expired in March 2016. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.