Orton Park Farm

2 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines2
Installed capacity1.6 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Orton Park Wind Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted April 2013 Permission granted July 2013 Under construction June 2016 Operational June 2017

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3359.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 12 months. The scheme has been operating for about 9 years. That works out at 0.8 MW per turbine on average.

Nearby

See all wind farms in Cumbria.