Parc Cynog Extension

5 turbines · operational · Dyfed

Wind farm facts

StatusOperational
County / regionDyfed
Turbines5
Installed capacity3.6 MW
Turbine capacity0.7 MW
Tip heightnot recorded
Operator (or applicant)Micon Wind Turbines (UK) Limited
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1997 1999 2001 2003 2005 2007 2009 2011 2013 Original scheme Application submitted May 1998 Permission granted February 2000 Operational February 2001 Later scheme Application submitted February 2006 Permission granted July 2007 Operational November 2009 Permission expired July 2012

From application to operation, this scheme took about 3 years.

The register links a second scheme on this site (REPD ref 2950, Operational): 6 turbines · 1.3 MW each · applicant Nuon. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2636.

What the register tells us

The application was determined in about 21 months. The scheme has been operating for about 25 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.72 MW per turbine on average.