7 turbines · operational · Lothian
| Status | Operational |
|---|---|
| County / region | Lothian |
| Turbines | 7 |
| Installed capacity | 14 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Your Energy |
| Turbine manufacturer | Vestas |
| Turbine model | V80 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
The register links a second scheme on this site (REPD ref 3363, Application Withdrawn): 2 turbines · 3 MW each · applicant Longhill Wind Farm Ltd. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3232.
The application was determined in about 11 months. Construction to first power took about 7 months. A planning permission on this site expired in June 2011. The scheme has been operating for about 16 years. That works out at 2 MW per turbine on average.
See all wind farms in Lothian.