Pigeon Top

9 turbines · revised · Co. Tyrone

Wind farm facts

StatusRevised
County / regionCo. Tyrone
Turbines9
Installed capacity20.7 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)TCI Renewables
Turbine manufacturerGE
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Scheme REPD 2710 Application submitted January 2009 Permission granted December 2010 Granted on appeal December 2010 Permission expired December 2010 Refused January 2015 Scheme REPD 4650 Application submitted September 2011 Permission granted November 2012 Under construction December 2015 Permission expired November 2017

The register links a second scheme on this site (REPD ref 4650, Under Construction): 9 turbines · 3 MW each · applicant Energia. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2710.

What the register tells us

The application was determined in about 23 months. The register records a refusal in January 2015 before the scheme progressed. Permission was ultimately granted on appeal in December 2010. A planning permission on this site expired in December 2010. That works out at 2.3 MW per turbine on average.