12 turbines · operational · Co. Tyrone
| Status | Operational |
|---|---|
| County / region | Co. Tyrone |
| Turbines | 12 |
| Installed capacity | 38.4 MW |
| Turbine capacity | 3.2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Energia |
| Turbine manufacturer | GE |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 12 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4107.
The application was determined in about 40 months. Construction to first power took about 30 months. The register records a refusal in October 2009 before the scheme progressed. Permission was ultimately granted on appeal in October 2009. A planning permission on this site expired in October 2013. The scheme has been operating for about 8 years. That works out at 3.2 MW per turbine on average.
See all wind farms in Co. Tyrone.