Pollnalaght (Cornavarrow)

12 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines12
Installed capacity38.4 MW
Turbine capacity3.2 MW
Tip heightnot recorded
Operator (or applicant)Energia
Turbine manufacturerGE
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted June 2006 Refused October 2009 Permission granted October 2009 Granted on appeal October 2009 Permission expired October 2013 Under construction December 2015 Operational June 2018

From application to operation, this scheme took about 12 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4107.

What the register tells us

The application was determined in about 40 months. Construction to first power took about 30 months. The register records a refusal in October 2009 before the scheme progressed. Permission was ultimately granted on appeal in October 2009. A planning permission on this site expired in October 2013. The scheme has been operating for about 8 years. That works out at 3.2 MW per turbine on average.