Quixwood Moor

13 turbines · operational · Borders

Wind farm facts

StatusOperational
County / regionBorders
Turbines13
Installed capacity29.9 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)NTR PLC
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted December 2011 Permission expired April 2012 Permission granted April 2013 Under construction January 2016 Operational March 2017

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4179.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 14 months. A planning permission on this site expired in April 2012. The scheme has been operating for about 9 years. That works out at 2.3 MW per turbine on average.