46 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 46 |
| Installed capacity | 289.8 MW |
| Turbine capacity | 6.3 MW |
| Tip height | 154 m |
| Operator (or applicant) | Orsted (formerly Dong Energy)/ Macquarie Group |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SWT-6.0-154 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 8 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2515.
The application was determined in about 42 months. Construction to first power took about 11 months. A planning permission on this site expired in July 2010. The scheme has been operating for about 9 years. That works out at 6.3 MW per turbine on average.