Rampion Offshore Wind Farm (Hastings Zone)

116 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines116
Installed capacity400 MW
Turbine capacity3.45 MW
Tip height140 m
Operator (or applicant) E.ON UK
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted March 2013 Permission granted July 2014 Under construction January 2016 Operational November 2017

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2520.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 22 months. The scheme has been operating for about 9 years. That works out at 3.45 MW per turbine on average.