116 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 116 |
| Installed capacity | 400 MW |
| Turbine capacity | 3.45 MW |
| Tip height | 140 m |
| Operator (or applicant) | E.ON UK |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2520.
The application was determined in about 16 months. Construction to first power took about 22 months. The scheme has been operating for about 9 years. That works out at 3.45 MW per turbine on average.