Robin Rigg East

28 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines28
Installed capacity84 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)E.ON UK
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Project timeline Application submitted June 2002 Permission granted June 2003 Under construction December 2006 Operational April 2010

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2496.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 40 months. The scheme has been operating for about 16 years. That works out at 3 MW per turbine on average.