114 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 114 |
| Installed capacity | 1075 MW |
| Turbine capacity | 9.2 MW |
| Tip height | not recorded |
| Operator (or applicant) | SSE / Seagreen Wind Energy Ltd |
| Turbine manufacturer | Vestas |
| Turbine model | V164-10.0 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 11 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2540.
The application was determined in about 55 months. Construction to first power took about 29 months. A planning permission on this site expired in May 2010. The scheme has been operating for about 3 years. That works out at 9.43 MW per turbine on average.
See all wind farms in Offshore.