Seegronan

6 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines6
Installed capacity13.8 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Seegronan Windfarm
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2007 2009 2011 2013 2015 2017 2019 2021 2023 Scheme REPD 4108 Application submitted August 2006 Permission granted January 2011 Permission expired January 2016 Under construction March 2016 Operational August 2016 Scheme REPD 3325 Application submitted July 2013 Permission granted June 2017 Granted on appeal June 2017 Permission expired June 2022

From application to operation, this scheme took about 10 years.

The register links a second scheme on this site (REPD ref 3325, Awaiting Construction): 3 turbines · 3 MW each · applicant Seegronan Windfarm. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4108.

What the register tells us

The application was determined in about 53 months. Construction to first power took about 5 months. A planning permission on this site expired in January 2016. The scheme has been operating for about 10 years. That works out at 2.3 MW per turbine on average.