Shantavny Scotch

7 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines7
Installed capacity16.1 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Tyrone Wind Energy Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted October 2007 Permission granted February 2012 Under construction August 2016 Permission expired February 2017 Operational March 2017

From application to operation, this scheme took about 10 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4325.

What the register tells us

The application was determined in about 52 months. Construction to first power took about 7 months. A planning permission on this site expired in February 2017. The scheme has been operating for about 9 years. That works out at 2.3 MW per turbine on average.