Wind farm facts

StatusRevised
County / regionFife
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip heightnot recorded
Operator (or applicant)RM Brown & Son Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 Original scheme Application submitted September 2011 Permission granted February 2013 Later scheme Application submitted February 2013 Permission granted January 2014 Permission expired January 2014 Under construction June 2014 Operational December 2014

The register links a second scheme on this site (REPD ref 4093, Operational): 1 turbines · 1.5 MW each · applicant Clenergy. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3845.

What the register tells us

The application was determined in about 17 months. That works out at 1.5 MW per turbine on average.