Slieve Divena Phase 1 Wind Farm

12 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines12
Installed capacity30 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Greencoat (formerly Infinis/SSE)
Turbine manufacturerNordex
Turbine modelN80

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 Project timeline Application submitted March 2005 Permission granted May 2007 Operational March 2009

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3245.

What the register tells us

The application was determined in about 26 months. The scheme has been operating for about 17 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Co. Tyrone.