100 turbines · under construction · Offshore
| Status | Under Construction |
|---|---|
| County / region | Offshore |
| Turbines | 100 |
| Installed capacity | 1400 MW |
| Turbine capacity | not recorded |
| Tip height | 252 m |
| Operator (or applicant) | RWE Renewables UK Limited |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SG 14-222 DD |
Siemens Gamesa · SG 14-222 DD · 100 turbines · 14 MW each · rotor 222 m
Source: offshorewind.biz, installation update, 2026-04, read on 2026-09-15. Corroborated by 2 further sources. OpenStreetMap tags shown elsewhere on this page differ from this record; the sources above prevail.
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
DevelopmentConstructionOperationAhead (repowering horizon at 22 years)
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6556.
The application was determined in about 17 months. That works out at 14 MW per turbine on average.
See all wind farms in Offshore.
| Data | Source | Extract |
|---|---|---|
| Site, capacity, status, planning milestones | Renewable Energy Planning Database (DESNZ, Open Government Licence v3) | Q2 2026, published 03/08/2026 |
| Turbine positions | OpenStreetMap contributors (ODbL) | 19/08/2026 |
| Manufacturer and model | OpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong. | 19/08/2026 |
Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.