13 turbines · operational · Co. Fermanagh
| Status | Operational |
|---|---|
| County / region | Co. Fermanagh |
| Turbines | 13 |
| Installed capacity | 19.5 MW |
| Turbine capacity | 1.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Greencoat UK Wind |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 3 years.
The register links a second scheme on this site (REPD ref 4688, Operational): 6 turbines · 1.5 MW each · applicant Greencoat UK Wind. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3130.
The application was determined in about 15 months. The scheme has been operating for about 21 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 1.5 MW per turbine on average.
See all wind farms in Co. Fermanagh.