Teeside Offshore Wind Farm

27 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines27
Installed capacity62 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)EDF Energy - Northern Offshore Windfarm Ltd
Turbine manufacturerSiemens Gamesa
Turbine modelSWT-2.3-93

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Permission expired September 2000 Application submitted March 2005 Permission granted September 2007 Under construction February 2012 Operational August 2013

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2514.

What the register tells us

The application was determined in about 30 months. Construction to first power took about 18 months. A planning permission on this site expired in September 2000. The scheme has been operating for about 13 years. That works out at 2.3 MW per turbine on average.