5 turbines · operational · Co. Fermanagh
| Status | Operational |
|---|---|
| County / region | Co. Fermanagh |
| Turbines | 5 |
| Installed capacity | 11 MW |
| Turbine capacity | 2.2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Energia |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 10 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4152.
The application was determined in about 81 months. Construction to first power took about 11 months. A planning permission on this site expired in December 2019. The scheme has been operating for about 8 years. That works out at 2.2 MW per turbine on average.
See all wind farms in Co. Fermanagh.