Teiges

5 turbines · operational · Co. Fermanagh

Wind farm facts

StatusOperational
County / regionCo. Fermanagh
Turbines5
Installed capacity11 MW
Turbine capacity2.2 MW
Tip heightnot recorded
Operator (or applicant)Energia
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted March 2008 Permission granted December 2014 Under construction August 2017 Operational July 2018 Permission expired December 2019

From application to operation, this scheme took about 10 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4152.

What the register tells us

The application was determined in about 81 months. Construction to first power took about 11 months. A planning permission on this site expired in December 2019. The scheme has been operating for about 8 years. That works out at 2.2 MW per turbine on average.