92 turbines · under construction · Offshore
| Status | Under Construction |
|---|---|
| County / region | Offshore |
| Turbines | 92 |
| Installed capacity | 1400 MW |
| Turbine capacity | not recorded |
| Tip height | not recorded |
| Operator (or applicant) | RWE Renewables UK Limited |
| Turbine manufacturer | Vestas |
| Turbine model | V236-15.0 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6483.
The application was determined in about 30 months. A planning permission on this site expired in December 2026. That works out at 15.22 MW per turbine on average.