Tormywheel

15 turbines · operational · Lothian

Wind farm facts

StatusOperational
County / regionLothian
Turbines15
Installed capacity30.75 MW
Turbine capacity2.05 MW
Tip height111 m
Operator (or applicant)BlackRock (formerly Muirhall Energy)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted February 2005 Permission granted June 2007 Under construction December 2015 Operational March 2017

From application to operation, this scheme took about 12 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4263.

What the register tells us

The application was determined in about 28 months. Construction to first power took about 15 months. The scheme has been operating for about 9 years. That works out at 2.05 MW per turbine on average.