Triton Knoll

90 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines90
Installed capacity857 MW
Turbine capacity9.5 MW
Tip height187 m
Operator (or applicant)Innogy
Turbine manufacturerVestas
Turbine modelV164-9.5

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Project timeline Application submitted February 2012 Permission granted July 2013 Permission expired July 2014 Under construction September 2018 Operational January 2022

From application to operation, this scheme took about 10 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2532.

What the register tells us

The application was determined in about 17 months. Construction to first power took about 40 months. A planning permission on this site expired in July 2014. The scheme has been operating for about 4 years. That works out at 9.52 MW per turbine on average.