90 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 90 |
| Installed capacity | 857 MW |
| Turbine capacity | 9.5 MW |
| Tip height | 187 m |
| Operator (or applicant) | Innogy |
| Turbine manufacturer | Vestas |
| Turbine model | V164-9.5 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 10 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2532.
The application was determined in about 17 months. Construction to first power took about 40 months. A planning permission on this site expired in July 2014. The scheme has been operating for about 4 years. That works out at 9.52 MW per turbine on average.