110 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 110 |
| Installed capacity | 659 MW |
| Turbine capacity | 6 MW |
| Tip height | 222 m |
| Operator (or applicant) | Orsted (formerly Dong Energy) |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SWT-7.0-154 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2533.
The application was determined in about 16 months. Construction to first power took about 17 months. A planning permission on this site expired in November 2019. The scheme has been operating for about 8 years. That works out at 5.99 MW per turbine on average.
See all wind farms in Offshore.