Wear Point

4 turbines · operational · Dyfed

Wind farm facts

StatusOperational
County / regionDyfed
Turbines4
Installed capacity8.2 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)John Laing Environmental Assets Group
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted October 2009 Permission granted May 2010 Permission expired May 2011 Under construction June 2012 Operational July 2014

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4661.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 25 months. A planning permission on this site expired in May 2011. The scheme has been operating for about 12 years. That works out at 2.05 MW per turbine on average.