Westnewton

3 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines3
Installed capacity6.2 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)Broadview Energy Limited
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted December 2008 Refused July 2010 Permission granted February 2011 Granted on appeal February 2011 Under construction September 2013 Operational May 2014

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4141.

What the register tells us

The application was determined in about 26 months. Construction to first power took about 8 months. The register records a refusal in July 2010 before the scheme progressed. Permission was ultimately granted on appeal in February 2011. The scheme has been operating for about 12 years. That works out at 2.07 MW per turbine on average.