🌬️ Onshore wind farm

Windy Standard III Wind Farm (Brockloch Rig Phase 2)
Dumfries and Galloway

Recorded in WhichWindTurbine: 20 wind turbines. Point the app at one of them to see its profile in real time.

20
turbines
87.6 MW
MW total
180 m
tip height

📍 20 turbines mapped — each dot is a turbine recorded in the database. Average position: 55.28578 N · 4.24476 W.

Windy Standard III Wind Farm (Brockloch Rig Phase 2)

20 turbines · under construction · Dumfries and Galloway

Wind farm facts

StatusUnder Construction
County / regionDumfries and Galloway
Turbines20
Installed capacity87.6 MW
Turbine capacitynot recorded
Tip height180 m
Operator (or applicant)Fred Olsen Renewables
Turbine manufacturerEnercon
Turbine modelE-138 EP3 and E-115 EP3 (split not established)
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

✓ Verified reference — turbine make and model

Enercon · E-138 EP3 and E-115 EP3 (split not established) · 20 turbines

Source: Renewables Now, turbine supplier selected by Fred. Olsen Renewables, 2025-03, read on 2026-09-19. Corroborated by 2 further sources. OpenStreetMap tags shown elsewhere on this page differ from this record; the sources above prevail.

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

20182020202220242026today1234
  1. 1Dec 2016 — Application submitted
  2. 2Mar 2021 — Permission granted
  3. 3Mar 2021 — Granted on appeal
  4. 4Apr 2025 — Under construction

The register also records a planning permission expiry in Mar 2027, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4615.

What the register tells us

The application was determined in about 51 months. Permission was ultimately granted on appeal in March 2021. A planning permission on this site expired in March 2027. That works out at 4.38 MW per turbine on average.

Nearby

See all wind farms in Dumfries and Galloway.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.