Windy Standard III Wind Farm (Brockloch Rig Phase 2)

20 turbines · under construction · Dumfries and Galloway

Wind farm facts

StatusUnder Construction
County / regionDumfries and Galloway
Turbines20
Installed capacity87.6 MW
Turbine capacitynot recorded
Tip height180 m
Operator (or applicant)Fred Olsen Renewables
Turbine manufacturerEnercon
Turbine modelE-115 EP3 E3 4.200

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Project timeline Application submitted December 2016 Permission granted March 2021 Granted on appeal March 2021 Under construction April 2025 Permission expired March 2027

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4615.

What the register tells us

The application was determined in about 51 months. Permission was ultimately granted on appeal in March 2021. A planning permission on this site expired in March 2027. That works out at 4.38 MW per turbine on average.

Nearby

See all wind farms in Dumfries and Galloway.