Wythegill Wind Turbine

1 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines1
Installed capacity2.3 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Airvolution Energy
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted April 2011 Refused December 2011 Permission granted October 2012 Granted on appeal October 2012 Permission expired October 2014 Under construction March 2015 Operational June 2015

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3832.

What the register tells us

The application was determined in about 18 months. Construction to first power took about 3 months. The register records a refusal in December 2011 before the scheme progressed. Permission was ultimately granted on appeal in October 2012. A planning permission on this site expired in October 2014. The scheme has been operating for about 11 years. That works out at 2.3 MW per turbine on average.