18 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 18 |
| Installed capacity | 64.8 MW |
| Turbine capacity | 3.6 MW |
| Tip height | not recorded |
| Operator (or applicant) | Orsted (formerly Dong Energy) |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SWT-3.6-107 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 2 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2489.
The application was determined in about 8 months. Construction to first power took about 3 months. The scheme has been operating for about 17 years. That works out at 3.6 MW per turbine on average.
See all wind farms in Offshore.