Kentish Flats 2

15 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines15
Installed capacity49.5 MW
Turbine capacity3.3 MW
Tip heightnot recorded
Operator (or applicant)Vattenfall
Turbine manufacturerVestas
Turbine modelV90-3.0

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 Project timeline Permission expired February 2011 Application submitted June 2012 Permission granted February 2013 Under construction November 2014 Operational September 2015

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2504.

What the register tells us

The application was determined in about 8 months. Construction to first power took about 10 months. A planning permission on this site expired in February 2011. The scheme has been operating for about 11 years. That works out at 3.3 MW per turbine on average.