Kype Muir Wind Farm

26 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines26
Installed capacity88.4 MW
Turbine capacity3.4 MW
Tip heightnot recorded
Operator (or applicant)Banks Renewables
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Scheme REPD 4643 Application submitted August 2011 Permission granted May 2014 Under construction February 2017 Permission expired May 2019 Operational September 2019 Scheme REPD 4628 Application submitted October 2014 Permission granted September 2016 Permission expired September 2016 Under construction June 2021 Operational October 2024

From application to operation, this scheme took about 8 years.

The register links a second scheme on this site (REPD ref 4628, Operational): 15 turbines · 4.48 MW each · 200 m tip height · applicant Banks Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4643.

What the register tells us

The application was determined in about 33 months. Construction to first power took about 31 months. A planning permission on this site expired in May 2019. The scheme has been operating for about 7 years. That works out at 3.4 MW per turbine on average.

Nearby