19 turbines · operational · Highland
| Status | Operational |
|---|---|
| County / region | Highland |
| Turbines | 19 |
| Installed capacity | 79.8 MW |
| Turbine capacity | 4.2 MW |
| Tip height | 149.9 m |
| Operator (or applicant) | Boralex/Infinergy |
| Turbine manufacturer | Vestas |
| Turbine model | V136 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 9 years.
The register links a second scheme on this site (REPD ref 7708, Operational): 5 turbines · 149.9 m tip height · applicant Infinergy / Boralex. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6005.
The application was determined in about 36 months. Permission was ultimately granted on appeal in June 2019. A planning permission on this site expired in May 2027. The scheme has been operating for about 1 year. That works out at 4.2 MW per turbine on average.