Pencloe Wind Farm

18 turbines · under construction · East Ayrshire

Wind farm facts

StatusUnder Construction
County / regionEast Ayrshire
Turbines18
Installed capacity81 MW
Turbine capacity4.5 MW
Tip height149.9 m
Operator (or applicant)North British Wind / Invenergy
Turbine manufacturerVestas
Turbine modelV136-4.5

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Project timeline Application submitted February 2015 Permission granted December 2018 Granted on appeal December 2018 Under construction February 2024 Permission expired August 2027

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4480.

What the register tells us

The application was determined in about 46 months. Permission was ultimately granted on appeal in December 2018. A planning permission on this site expired in August 2027. That works out at 4.5 MW per turbine on average.