Penmanshiel Wind Farm

14 turbines · operational · Borders

Wind farm facts

StatusOperational
County / regionBorders
Turbines14
Installed capacity28.7 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted October 2011 Refused September 2012 Permission granted October 2013 Granted on appeal October 2013 Under construction May 2015 Operational July 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4600.

What the register tells us

The application was determined in about 24 months. Construction to first power took about 14 months. The register records a refusal in September 2012 before the scheme progressed. Permission was ultimately granted on appeal in October 2013. The scheme has been operating for about 10 years. That works out at 2.05 MW per turbine on average.