Strathy Wood

13 turbines · under construction · Highland

Wind farm facts

StatusUnder Construction
County / regionHighland
Turbines13
Installed capacity62.4 MW
Turbine capacity4.8 MW
Tip height180 m
Operator (or applicant)E.ON Renewables
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Project timeline Application submitted September 2015 Permission granted December 2021 Under construction January 2024 Permission expired December 2027

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4584.

What the register tells us

The application was determined in about 75 months. A planning permission on this site expired in December 2027. That works out at 4.8 MW per turbine on average.