27 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 27 |
| Installed capacity | 62 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | EDF Energy - Northern Offshore Windfarm Ltd |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SWT-2.3-93 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 8 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2514.
The application was determined in about 30 months. Construction to first power took about 18 months. A planning permission on this site expired in September 2000. The scheme has been operating for about 13 years. That works out at 2.3 MW per turbine on average.