Wether Hill

14 turbines · operational · Dumfries and Galloway

Wind farm facts

StatusOperational
County / regionDumfries and Galloway
Turbines14
Installed capacity18.2 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)Scottish Power/CRE Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Original scheme Application submitted January 2004 Permission granted March 2005 Under construction August 2006 Operational May 2007 Later scheme Application submitted December 2015

From application to operation, this scheme took about 3 years.

The register links a second scheme on this site (REPD ref 4487, Application Withdrawn): 11 turbines · 2 MW each · 100 m tip height · applicant Scottish Power Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4519.

What the register tells us

The application was determined in about 14 months. Construction to first power took about 9 months. The scheme has been operating for about 19 years. That works out at 1.3 MW per turbine on average.