Brenig Wind Farm

16 turbines · revised · Denbighshire

Wind farm facts

StatusRevised
County / regionDenbighshire
Turbines16
Installed capacity40 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Wind Power Wales
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Original scheme Application submitted April 2007 Permission granted January 2008 Later scheme Application submitted June 2015 Refused November 2015 Permission granted May 2016 Granted on appeal May 2016 Under construction August 2017 Permission expired May 2018 Operational October 2018

The register links a second scheme on this site (REPD ref 5598, Operational): 16 turbines · 2.35 MW each · 110 m tip height · applicant CGNEE. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4082.

What the register tells us

The application was determined in about 9 months. That works out at 2.5 MW per turbine on average.