Tir Mostyn And Foel Goch Wind Farm

25 turbines · operational · Clwyd

Wind farm facts

StatusOperational
County / regionClwyd
Turbines25
Installed capacity21.3 MW
Turbine capacity0.85 MW
Tip heightnot recorded
Operator (or applicant)Munich Re (previously Windjen Power Ltd)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1998 1999 2000 2001 2002 2003 2004 2005 2006 Project timeline Application submitted September 1999 Permission granted December 2002 Operational June 2005

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4689.

What the register tells us

The application was determined in about 39 months. The scheme has been operating for about 21 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.85 MW per turbine on average.