14 turbines · operational · Co. Tyrone
| Status | Operational |
|---|---|
| County / region | Co. Tyrone |
| Turbines | 14 |
| Installed capacity | 32.2 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Greencoat (formerly Energia Renewables) |
| Turbine manufacturer | Enercon |
| Turbine model | E70 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 8 years.
The register links a second scheme on this site (REPD ref 4562, Application Refused): 6 turbines · 2.5 MW each · applicant DW consultancy. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4041.
The application was determined in about 30 months. Construction to first power took about 13 months. A planning permission on this site expired in June 2013. The scheme has been operating for about 14 years. That works out at 2.3 MW per turbine on average.
See all wind farms in Co. Tyrone.