Dersalloch

23 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines23
Installed capacity69 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Scottish Power Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted July 2005 Permission granted July 2014 Under construction September 2015 Operational August 2016

From application to operation, this scheme took about 11 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4269.

What the register tells us

The application was determined in about 108 months. Construction to first power took about 11 months. The scheme has been operating for about 10 years. That works out at 3 MW per turbine on average.