17 turbines · operational · Humberside
| Status | Operational |
|---|---|
| County / region | Humberside |
| Turbines | 17 |
| Installed capacity | 34.9 MW |
| Turbine capacity | 2.05 MW |
| Tip height | not recorded |
| Operator (or applicant) | RWE Npower Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4070.
The application was determined in about 28 months. Construction to first power took about 15 months. A planning permission on this site expired in May 2013. The scheme has been operating for about 10 years. That works out at 2.05 MW per turbine on average.
See all wind farms in Humberside.