Tween Bridge Windfarm

22 turbines · operational · South Yorkshire

Wind farm facts

StatusOperational
County / regionSouth Yorkshire
Turbines22
Installed capacity44 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)E.ON Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Project timeline Application submitted January 2004 Permission granted February 2008 Under construction May 2011 Operational February 2012

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3928.

What the register tells us

The application was determined in about 49 months. Construction to first power took about 9 months. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.