19 turbines · revised · West Glamorgan
| Status | Revised |
|---|---|
| County / region | West Glamorgan |
| Turbines | 19 |
| Installed capacity | 57 MW |
| Turbine capacity | 3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Npower Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
The register links a second scheme on this site (REPD ref 4648, Operational): 16 turbines · 2.05 MW each · applicant RWE Npower Renewables/ Innogy. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2947.
The register records a refusal in January 2010 before the scheme progressed. That works out at 3 MW per turbine on average.