Westermost Rough A

35 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines35
Installed capacity210 MW
Turbine capacity6 MW
Tip heightnot recorded
Operator (or applicant)Orsted (formerly Dong Energy)
Turbine manufacturerSiemens Gamesa
Turbine modelSWT-6.0-154

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted November 2009 Permission granted November 2011 Under construction February 2014 Operational May 2015

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2545.

What the register tells us

The application was determined in about 24 months. Construction to first power took about 15 months. The scheme has been operating for about 11 years. That works out at 6 MW per turbine on average.