Harburnhead Wind Farm

22 turbines · operational · Lothian

Wind farm facts

StatusOperational
County / regionLothian
Turbines22
Installed capacity51.7 MW
Turbine capacity2.35 MW
Tip height126 m
Operator (or applicant)Gresham House
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Permission expired July 2010 Application submitted December 2011 Permission granted July 2014 Under construction February 2016 Operational December 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4225.

What the register tells us

The application was determined in about 31 months. Construction to first power took about 10 months. A planning permission on this site expired in July 2010. The scheme has been operating for about 10 years. That works out at 2.35 MW per turbine on average.