13 turbines · operational · Northumberland
| Status | Operational |
|---|---|
| County / region | Northumberland |
| Turbines | 13 |
| Installed capacity | 26 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Scottish Power Renewables |
| Turbine manufacturer | proven |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 6 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3752.
The application was determined in about 26 months. Construction to first power took about 21 months. The register records a refusal in May 2007 before the scheme progressed. Permission was ultimately granted on appeal in January 2009. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.